![]() ![]() Timeline for Carousel Numinous Production
Week July 12th and 13th - All Angle iron for spokes, kickers and
rafters will be cut and drilled in San Rafael. Time will continue working
on the Tower Base. We NEED BIKES and 2x4s!
Week of July 19th - Middle panels constructed at Bird's Nest including
gears. We NEED BIKES and 2x4s! Roof panels painted.
Weekend July 19th and 20th - Any remaining Carousel Fabrication in San
Rafael. All Roof Metal cut in SF. Cone Structures worked on in SF.
the week, build the mecha to spin on middle panels.
Weekend July 26th, 27th - Electrical, Cone and mecha finished for all
Carousels at SF. Sound soldering, taping events, installing speakers.
Weekend August 2nd, 3rd - Cone Structures and mecha at the Birds Nest.
Continue Tower needs to be finished this weekend. Sound soldering, taping
events, installing speakers.
Week August 9th - Wiring, testing, installing Sound boxes, touch up. Prepare Bar
for the playa.
Week August 16th - last minuts stuff, begin preparing bar and racks for cars, loading.
August 20
|